Ward: West End
Streets Affected: Regent Place, Regent Street, Warwick Street
Project Type: Developer and third party funded
Project Overview
The Warwick Street Phase 2 works were a continuation of the streetscape improvement works undertaken in Phase 1 associated with the redevelopment of Chesham House.
The streetscape improvement works consisted of the following:
- Pedestrianisation of Regent Place between Regent Street and Warwick Street
- Resurfacing the existing carriageway in Warwick Street;
- Repaving the existing footway in Warwick Street and Regent Place using high quality materials;
- Improving pedestrian access through Regent Place;
- Upgrading of street lighting and improving drainage;
- Increasing cycle parking facilities; and
- Reducing street clutter by installing wall mounted street lighting
Status
Works completed
Outline Programme
November 2008 - June 2009
Project Documents
Warwick Street - Scheme Board.pdf - (282 kb)
STATUS
On Hold
Design Stage
In Consultation
Works on site
Works completed