Cookie Consent by Free Privacy Policy Generator website

Warwick Street Phase 2

Warwick Street Phase 2

Ward: West End

Streets Affected: Regent Place, Regent Street, Warwick Street

Project Type: Developer and third party funded

Project Overview

The Warwick Street Phase 2 works were a continuation of the streetscape improvement works undertaken in Phase 1 associated with the redevelopment of Chesham House. 

The streetscape improvement works consisted of the following:

  • Pedestrianisation of Regent Place between Regent Street and Warwick Street
  • Resurfacing the existing carriageway in Warwick Street;
  • Repaving the existing footway in Warwick Street and Regent Place using high quality materials;
  • Improving pedestrian access through Regent Place;
  • Upgrading of street lighting and improving drainage;
  • Increasing cycle parking facilities; and
  • Reducing street clutter by installing wall mounted street lighting

Status

Works completed

Outline Programme

November 2008 - June 2009

Project Documents

STATUS

    On Hold
    Design Stage
    In Consultation
    Works on site
    Works completed