Strand Aldwych Streetscape Improvements

Strand Aldwych Streetscape Improvements

Ward: St James's

Streets Affected: Lancaster Place, Strand

Project Type: Streetscape

Project Overview

The City Council is carrying out works to improve the streetscape and traffic management on Strand.

The works include the following:

  • Providing a right turn for buses from Strand eastbound to Lancaster Place southbound
  • Providing additional signal controlled pedestrian crossings, including green man phases, at the junction
  • Reconstruction of the Strand southern side footway with high quality materials
  • Dedicated loading pad
  • Reducing street clutter

Status

Works completed

Outline Programme

Coordinating the scheme with TfL and incorporating it into the ORN. Works commenced in November 2011 and were completed in August 2013.