Project Overview

FM Conway, working on behalf of Westminster City Council, will be carrying out highway improvement works outside 21-22 Boston Place.

The highway improvements include the following:

  • Removal of three bollards outside the development;
  • Repaving the footway in concrete paving; and
  • Installation of new granite kerbs along the extent of the works.

Status

Works completed

Outline Programme

Works will commence on site on 3rd October 2016 and to be completed within 2 weeks.