Ward: West End
Streets Affected: Broadwick Street
Project Type: Streetscape
Project Overview
Westminster City Council is proposing footway and carriageway improvements in Broadwick St.
The improvements include the following:
- Repaving of footway in Yorkstone paving;
- Reinstatement of traffic signs and road markings renewals.
- Reinstatement of granite setts on the carriageway;
- Drainage upgrades;
- Relocation of existing lighting column;
- Reinstallation of John Snow hand pump;
- Extension of existing buildout; and
- Relocation of parking bay
Status
Works completed
Outline Programme
Works will commence on site on 26th February 2018 and to be completed by 13th July 2018
Project Documents
There are no documents available for this project