Project Overview

The scheme forms part of the Section 106 works for the development of Mercer’s Yard and includes providing a flush footway and carriageway for the length of Langley Street and will be undertaken by Westminster City Council.

The works include:

  • Installation of new Yorkstone setts in the footway and flush granite kerbs along Langley Street; and
  • Installation of new granite setts in the carriageway flush with the footway along Langley Street.
  • Refurbishment of existing lanterns to current Westminster City Council standards

Status

Works completed

Outline Programme

Works will commence on site on 20th August 2018 and to be completed by 31st January 2019