Ward: Marylebone
Streets Affected: Portman Square
Project Type: Streetscape
Project Overview
The works will consist of upgrading the existing footway with high quality yorkstone material to improve pedestrian safety and provide a more pleasant surface which better aligns with the profile of the area.
Status
Works completed
Outline Programme
The construction works are programmed to commence Monday 27th January and expected to be complete in October 2020. Works will take place during standard working hours Monday to Friday 8am to 5pm and Saturdays 9am to 1pm. Construction will be carried out in two phases:
Phase 1 (27/01/2020 to early June). West and South footways of the square.
Phase 2 (early June to October). North and East footways of the square.
Project Documents
There are no documents available for this project