Portman Square Footways

Portman Square Footways

Ward: Marylebone

Streets Affected: Portman Square

Project Type: Streetscape

Project Overview

The works will consist of upgrading the existing footway with high quality yorkstone material to improve pedestrian safety and provide a more pleasant surface which better aligns with the profile of the area. 

Status

Works completed

Outline Programme

The construction works are programmed to commence Monday 27th January and expected to be complete in October 2020. Works will take place during standard working hours Monday to Friday 8am to 5pm and Saturdays 9am to 1pm. Construction will be carried out in two phases:

Phase 1 (27/01/2020 to early June). West and South footways of the square.

Phase 2 (early June to October). North and East footways of the square.