Project Overview

Threshold review and design review of the public realm proposals associated with the redevelopment of the Bow Street Magistrates Court. Works are proposed on four frontages: Bow Street, Martlett Court, Crown Court and Board Court.

In additional Contract B will review the lighting design proposals and Contract E will progress TMOs for parking layout changes on Bow Street.
 
Works will be implemented in 6 phases.

The improvements include the following:

  • Repaving the footway of Bow Street in York Stone Pavers;
  • Repaving the footway of Marlett Court and Crown Court in concrete paving flags;
  • Resurfacing of part of Bow Street carriageway in hot rolled asphalt;
  • Changes to parking provisions to accommodate new resident and pay-by-phone parking bays;
  • Improving the surface water drainage along the whole extents of the scheme; and
  • Upgrading public lighting.

Status

Works completed

Outline Programme

Phase 1: 06/04/2020 - 26/06/2020
Phase 2: 06/04/2020 - 15/05/2020
Phase 3: 18/05/2020 - 05/06/2020
Phase 4: 08/06/2020 - 26/06/2020
Phase 5: 29/06/2020 - 24/07/2020
Phase 6: 27/07/2020 - 28/07/2020

Project Documents

There are no documents available for this project

STATUS

    On Hold
    Design Stage
    In Consultation
    Works on site
    Works completed