Lanark Road - Public Realm improvement

Lanark Road - Public Realm improvement

Ward: Maida Vale

Streets Affected: Lanark Road

Project Type: Streetscape

Project Overview

Highway works are required for a new development at 221-235 Lanark Road. The works include reinstatement of footway and carriageway with alterations to the existing vehicle crossovers location, drainage and lighting upgrading and reinstatement of two new trees.

Status

Works completed

Outline Programme

Footway works:
PHASE 1: Northern footway 30/09/2020 - 22/10/2020
Carriageway Construction: 30/09/2020 - 13/10/2020
PHASE 2: Northern footway 14/10/2020 - 03/11/2020
PHASE 3: Northern footway 14/10/2020 - 27/10/2020
PHASE 1: Southern footway 28/10/2020 - 10/11/2020
PHASE 2: Southern footway 11/11/2020 - 24/11/2020
Carriageway surfacing: 25/11/2020 - 27/11/2020