19/20 Coventry Street and Haymarket

19/20 Coventry Street and Haymarket

Ward: St James's

Streets Affected: Coventry Street, Haymarket

Project Type: Traffic, Safety & Parking

Project Overview

These improvement works include:

  • Kerb Buildout on northern footway to improve pedestrian safety;
  • New diagonal pedestrian crossing to improve crossing facilities
  • Raised table entrance on Coventry Street east
  • New loading pads to provide better loading facilities for businesses
To accommodate the majority of these works; lane closures will be used maintaining all movements. Coventry Street will be closed for 5 weeks. Night works are proposed for
resurfacing and Antiskid.

Status

Works on site

Outline Programme

January 2021 - June 2021

Project Documents

STATUS

    On Hold
    Design Stage
    In Consultation
    Works on site
    Works completed