Ward: Marylebone
Streets Affected: Chiltern Street, Paddington Street
Project Type: Traffic, Safety & Parking
Project Overview
Westminster City Council has commissioned its service provider, FM Conway Limited, to carry out public realm improvement works at the junction of Paddington Street & Chiltern Street.
The planned improve-ments include:
- Construction of new kerb buildouts
- Installation of a raised table
- Enhancements to pedestrian crossing points
- Changes to parking and loading arrangements
- Footway resurfacing
- Introduction of trees
- Introduction of a new zebra crossing
Status
Works on site
Outline Programme
15th June 2026 - 1st September 2026
Project Documents
There are no documents available for this project
STATUS
On Hold
Design Stage
In Consultation
Works on site
Works completed